Guide for tradies · NSW

DA, CDC or construction certificate: which one means work is close?

A construction certificate means work is close. In NSW a construction certificate is needed before building work starts on a job with development consent, and a complying development certificate is the planning and building approval in one. A development application is the earliest stage: consent has only been asked for.

What is a development application (DA)?

A DA asks the consent authority, usually the council, for permission to carry out development. It is the earliest point a job shows up on the register, often months before a builder is on site, and some are refused. Last week 530 DAs were lodged across NSW.

What is a complying development certificate (CDC)?

The NSW Government describes complying development as "a combined planning and construction approval for straightforward development that can be determined through a fast-track assessment by a council or an accredited certifier". The standard assessment period is 20 days. A CDC job does not need a separate construction certificate, so it can move to site quickly. Last week 628 CDCs were lodged across NSW.

Source: NSW Department of Planning, Complying development, opened 14 November 2026.

What is a construction certificate (CC)?

The NSW Government says a construction certificate "confirms your construction plans and development specifications are consistent with the development consent, and comply with the Building Code of Australia", and that if your building work needs development consent, "you can't start until" a construction certificate has been issued. It can be provided by the council or a registered certifier. Last week 554 CCs were lodged across NSW.

Source: NSW Government, Approvals needed for your building project, opened 14 November 2026.

Which ones should a tradie go after first?

  1. Construction certificatesThe job has consent and the plans are being certified: the build is close, and the owner is choosing trades now.
  2. Complying development certificatesPlanning and building approval together, often a pool, a granny flat or a new home, and often quick to start.
  3. Development applicationsEarly. A first flyer now, and a second when the same address lodges its construction certificate. The JustLodged dashboard flags that moment as a go back alert.

Queensland and the ACT

In Logan and on the Sunshine Coast, most homes are approved by a private building certifier, and those building approvals are lodged with the council; JustLodged lists them with Logan's new development applications. In Brisbane, Ipswich, Redland, Toowoomba and Western Downs the list is the development applications lodged with the council, read from each council's public application register. In the ACT the list is development applications lodged with the ACT Government.

Questions

What is the difference between a DA, a CDC and a construction certificate?
A development application (DA) asks for development consent. A complying development certificate (CDC) is a combined planning and construction approval for straightforward work. A construction certificate (CC) confirms the building plans match the consent and the Building Code of Australia, and is needed before building work starts.
Which one means work is about to start?
The construction certificate. NSW requires one before building or construction work starts on a DA approved job, so a CC lodged last week is usually the closest thing on the register to a start date. A CDC is also close, because it is the planning and construction approval in one.
Does a CDC job also need a construction certificate?
No. The NSW Government says you don't need a construction certificate if you have a CDC.
Who issues them?
A construction certificate can be provided by the council or a registered certifier. A complying development certificate can be issued by the council or a registered certifier, in as little as 20 days.

Other areas and trades

Adelaide east · Adelaide Hills · Adelaide north · Adelaide south · Adelaide west · Ballarat and Bendigo · Brisbane · Canberra and Queanbeyan · Central Coast and Lake Macquarie · Geelong and the Surf Coast · Illawarra · Inner Melbourne and Bayside · Ipswich and Redland · Lockyer Valley · Logan and the Sunshine Coast · Macarthur and south west Sydney · Melbourne east · Melbourne north · Melbourne south east · Melbourne west · Mornington Peninsula · Newcastle and the Hunter · Northern Beaches · Toowoomba and the Western Downs · Western Sydney